Champa Mahila Society

ABSTRACT ESTIMATE FOR THE CONSTRUCTION OF THE CHAMPA MAHILA SOCIETY (HANDICAPPED) HOSTEL BUILDING
MOUZA: SIBGANJ, DAG NO: 103/1319, 103/1246, KHATIN NO: 190.191 P.S.: BASANTI, DIST.: SOUTH 24 PARGANAS

No Description of Work Qty Unit  Rs./unit Amount (Rs)
1 Earthwork in excavation of foundation in all kinds of soil, including ramming and dressing complete as per direction 73.780 M^3 34.04 2,511.47
2 Earth filling and floor area in layer not exceeding 15 cm including watering and ramming complete (silver sand). 66.871 M^3 150.00 10,030.65
3 Brick flat soling in foundation and floor area with picked jhama bricks 173.062 M^2 105.00 18,171.51
4 Cement concrete with graded jhama chips 20 mm in sizes, excluding cost of shuttering and reinforcement. 17.272 M^3 1,818.00 31,400.50
5 Brick work in foundation with (1:6) cement and sand mortar and with 1st class brick. 7.600 M^3 1,794.00 13,634.40
6 25 mm thick damp proof course (1:2:4) with 6 mm down stone chips and admixer with water proofing compound 21.599 M^2 75.00 1,619.93
7 Brick work in super structure with 1st class brick and with 1:6 cement and sand mortar 49.776 M^3 1,848.00 91,986.05
8 Shuttering with centering 25 mm thick hard wood plank, using approved stout and props and striking out after completion of the work. 435.800 M^2 123.00 53,603.40
9 Cement concrete with graded stone chips 20 mm in sizes (1:2:4) excluding shuttering. 49.641 M^3 2,658.00 131,945.78
10 Reinforcement for R.C.C. work in all sorts of structure including bending, binding with black annalead wire and proper placing in position. 4676.000 Kg 22.91 107,127.16
11 10 mm th. cement plastering in ceiling with 1:4 cement and sand mortar including rounding off corner. 193.610 M^2 47.00 9,099.67
12 20 mm thick cement plastering to wall with 1:6 cement and sand mortar including rounding off corner. 277.600 M^2 59.00 16,378.40
13 15 mm thick cement plaster to outside wall with 1:6 cement and sand mortar including rounding off corner. 186.480 M^2 55.00 10,256.40
14 Sal wood work for doors' and windows' frame.  0.483 M^3 32,458.00 15,680.46
15 Shutters for doors and windows 35 mm th. 25 mm panel. 27.370 M^2 1,289.00 35,279.93
16 125 mm thick brick work with 1st class brick and 1:5 cement and sand mortar including racking out joints. 36.090 M^2 230.00 8,300.70
17 25 mm thick artificial stone flooring, dado etc; (1:2:4) cement concrete with (6 mm down) stone chips, laid in panel including leveling and 3 mm thick topping and smooth finishing complete. 125.500 M^2 102.00 12,801.00
18 M.S. Ornamental grill works for windows and hand railing, 14 kgs/16 kgs/ sqmt.  42.930 M^2 560.00 24,040.80
19 White washing with slaked lime. 1/2 coats. 657.690 M^2 2.91 1,913.88
20 Color washing with base pigment (Snowcem) 186.480 M^2 8.60 1,603.73
Total       597,385.80
21 Adding 22.5% for Riverine area rate of item 3 to 20 584,843.68   0.225 131,589.83
Adding 3% for Electricity of item 1 to 20 597,385.80   0.03 17,921.57
Grand Total       746,897.21
  In USD ($1 = Rs. 45)       16,597.72

CMS home

 

<< Asha-Seattle Home